WW Date Exterior Interior
9760 200
Completed to date 4222 203
% completion 43.3% 100%
40 3Oct - 9Oct 103 127
41 10Oct - 16Oct 90 127
42 17Oct - 23Oct 70 127
43 24Oct - 30Oct 112 127
44 31st - 6Nov 372 127
45 7Nov - 13Nov 287 127
46 14Nov - 20Nov 579 127
47 21Nov - 27Nov 534 140
48 28Nov - 5Dec 675 145
49 6Dec - 10Dec 509 201
50 11 Dec -19 Dec 476 201
51 20 Dec - 26 Dec 336 203

Milestones

Highlights

  1. Found new defective tiles submit pictures to Roman

Link to Defect file

  1. Survey AHU room found 5 slabs, will collect data and check whether there are brackets under the slab

Plan Next week

  1. Continue work on Side C and Scaffolding

Issues

  1. L-23 Gondola for Facade C is down since 21Oct . Parts will arrive 13th Feb 2023

Open Action

Untitled