| WW |
Date |
Exterior |
Interior |
|
|
9760 |
200 |
| Completed to date |
|
4222 |
203 |
| % completion |
|
43.3% |
100% |
| 40 |
3Oct - 9Oct |
103 |
127 |
| 41 |
10Oct - 16Oct |
90 |
127 |
| 42 |
17Oct - 23Oct |
70 |
127 |
| 43 |
24Oct - 30Oct |
112 |
127 |
| 44 |
31st - 6Nov |
372 |
127 |
| 45 |
7Nov - 13Nov |
287 |
127 |
| 46 |
14Nov - 20Nov |
579 |
127 |
| 47 |
21Nov - 27Nov |
534 |
140 |
| 48 |
28Nov - 5Dec |
675 |
145 |
| 49 |
6Dec - 10Dec |
509 |
201 |
| 50 |
11 Dec -19 Dec |
476 |
201 |
| 51 |
20 Dec - 26 Dec |
336 |
203 |
Milestones
Highlights
- ~ 70% of the time is raining last week. Slowed our progress
| 11/8/2022 |
Day Shift |
Yes |
| 11/8/2022 |
Night Shift |
Yes |
| 11/9/2022 |
Day Shift |
No |
| 11/9/2022 |
Night Shift |
No |
| 11/10/2022 |
Day Shift |
Yes |
| 11/10/2022 |
Night Shift |
Yes |
| 11/11/2022 |
Night Shift |
Yes |
| 11/12/2022 |
Night Shift |
No |
| 11/13/2022 |
Night Shift |
Yes |
| 11/14/2022 |
Night Shift |
Yes |
- Found new defective tiles submit pictures to Roman
Link to Defect file
Plan Next week
- Continue work on Side A
- Implement 2nd system onto 1 gondola. Target to increase throughput by another ~1.5x - 1.8x
Issues
- L-23 Gondola for Facade C is down since 21Oct till the weekends.
Open Action
Untitled