WW Date Exterior Interior
9760 200
Completed to date 4222 203
% completion 43.3% 100%
40 3Oct - 9Oct 103 127
41 10Oct - 16Oct 90 127
42 17Oct - 23Oct 70 127
43 24Oct - 30Oct 112 127
44 31st - 6Nov 372 127
45 7Nov - 13Nov 287 127
46 14Nov - 20Nov 579 127
47 21Nov - 27Nov 534 140
48 28Nov - 5Dec 675 145
49 6Dec - 10Dec 509 201
50 11 Dec -19 Dec 476 201
51 20 Dec - 26 Dec 336 203

Milestones

Highlights

  1. ~ 70% of the time is raining last week. Slowed our progress
Date Shift Raining?
11/3/2022 Night Shift Yes
11/4/2022 Day Shift No
11/4/2022 Night Shift Yes
11/5/2022 Day Shift Yes
11/6/2022 Night Shift Yes
11/6/2022 Day Shift Yes
11/6/2022 Night Shift No
11/7/2022 Day Shift Yes
11/7/2022 Night Shift Yes
  1. Found number of defective tiles submit pictures to Roman

Plan Next week

  1. Continue work on Side A
  2. Implement 2nd system onto 1 gondola. Target to increase throughput by another ~1.5x - 1.8x
  3. Provide pillar scan report to Er. Lee
  4. Start 1x vacant office unit #17-03

Issues

  1. Need another 10 office units from Shaw to complete indoor scan target of 200
  2. L-23 Gondola for Facade C is down since 21Oct till the weekends.

Open Action

Untitled