Milestones

Highlights

  1. Started Side A
  2. 29 Oct - Implemented larger scanner (1m x 40cm), see ~1.5x improvement. Need to optimize to get higher output

https://youtu.be/prwODxLID6E

  1. Open action plan to increase output
    1. This week - 7 x 24 shift
    2. 7th Nov - Implement 2nd larger scanner in 1 gondola

Plan Next week

  1. Continue work on Side A
  2. Continuous improvement enhanced hardware and procedure to speed up scanning

Issues

  1. Not able to perform perform pillar scan due to ongoing works, area not assessable
  2. Able to start 24 x 7 shift work from 2 Nov, awaiting clearance from safety
  3. Need another 10 office units from Shaw to complete indoor scan target of 200
  4. L-23 Gondola for Facade C is down since 21Oct till the weekends.

Open Action

Untitled