Milestones
Highlights
- Started Side A
- 29 Oct - Implemented larger scanner (1m x 40cm), see ~1.5x improvement. Need to optimize to get higher output
https://youtu.be/prwODxLID6E
- Open action plan to increase output
- This week - 7 x 24 shift
- 7th Nov - Implement 2nd larger scanner in 1 gondola
Plan Next week
- Continue work on Side A
- Continuous improvement enhanced hardware and procedure to speed up scanning
Issues
- Not able to perform perform pillar scan due to ongoing works, area not assessable
- Able to start 24 x 7 shift work from 2 Nov, awaiting clearance from safety
- Need another 10 office units from Shaw to complete indoor scan target of 200
- L-23 Gondola for Facade C is down since 21Oct till the weekends.
Open Action