Milestones

Date Exterior Interior
9760 200
Completed to date 375 127
% completion 4% 64%
40 3Oct - 9Oct 103 127
41 10Oct - 16Oct 90 127
42 17Oct - 23Oct 70 127
43 24Oct - 30Oct 112 127
44 31st - 6Nov

Highlights

  1. Started Side A
  2. 29 Oct - Implemented larger scanner (1m x 40cm), see ~1.5x improvement. Need to optimize to get higher output

https://youtu.be/prwODxLID6E

  1. Open action plan to increase output
    1. This week - 7 x 24 shift
    2. 7th Nov - Implement 2nd larger scanner in 1 gondola

Plan Next week

  1. Continue work on Side A
  2. Continuous improvement enhanced hardware and procedure to speed up scanning

Issues

  1. Not able to perform perform pillar scan due to ongoing works, area not assessable
  2. Able to start 24 x 7 shift work from 2 Nov, awaiting clearance from safety
  3. Need another 10 office units from Shaw to complete indoor scan target of 200
  4. L-23 Gondola for Facade C is down since 21Oct till the weekends.

Open Action

Untitled