Milestones
| WW |
Date |
Exterior |
Interior |
|
|
9760 |
200 |
| Completed to date |
|
263 |
127 |
| % completion |
|
3% |
64% |
| 40 |
3Oct - 9Oct |
103 |
127 |
| 41 |
10Oct - 16Oct |
90 |
127 |
| 42 |
17Oct - 23Oct |
70 |
127 |
| 43 |
24Oct - 30Oct |
|
|
| 44 |
31st - 6Nov |
|
|
|
|
|
|
Highlights
- Started Side A and C
- Testing and improvement of scanner for facade
- Automated suction caps system (by middle week 42) waiting for materials
- Larger scanner area 40cm x 40cm to 100cm x 40cm (1st set by middle week 42)
Plan Next week
- Continue work on Side A and C facade scan
- Perform pillar scan above 2m to detect for pins and tie back.
- Implement enhanced hardware and improvement to speed up scanning
Issues
- Need another 10 office units from Shaw to complete indoor scan target of 200
- L-23 Gondola for Facade C is down since Friday till the weekends.
Open Action