Milestones
| WW |
Date |
Exterior |
Interior |
|
|
9760 |
200 |
| 40 |
3Oct - 9Oct |
103 |
127 |
| 41 |
10Oct - 16Oct |
90 |
|
| 42 |
17Oct - 23Oct |
|
|
| 43 |
24Oct - 30Oct |
|
|
| 44 |
31st - 6Nov |
|
|
Highlights
- Started Side A facade scan
- Testing and improvement of scanner for facade
- Faster scanning speed 40cm x 40cm (90sec to 45sec) Done
- Automated suction caps system (by middle week 42) waiting for materials
- Larger scanner area 40cm x 40cm to 100cm x 40cm (1st set by middle week 42)
- Redo pillar scan using robotic arm platform to improve consistency of data
Plan Next week
- Continue work on Side A and C facade scan
- Implement enhanced hardware and improvement to speed up scanning
- Commercial and technical proposal for pillar scan
Issues
- Need another 10 office units from Shaw to complete indoor scan target of 200
- Intermittent issues with gantry
- Motor driver loose (New connectors)
- Controller overheat (New cooling system - Done)
Open Action
Untitled