WW Date Exterior
9797
Completed to date 9697
% completion 99%
12 20 - 26Mar 672
13 27Mar - 2Apr 1080
14 3Apr - 9Apr 383
15 10Apr - 16Apr 0
16 17 - 23Apr 0
17 24Apr -30Apr 892
18 1May - 8May 1526
19 9May - 15May 894

Milestones

Highlights

  1. Submit Method of Statement, will operate new platform (Robot wall crawler) from Wednesday

Untitled

  1. ound new defective tiles submit pictures to Roman

Link to Defect file

Plan Next week

  1. Continue work on Side D/C

Issues

Open Action

Untitled