WW Date Exterior
9797
Completed to date 9697
% completion 99%
12 20 - 26Mar 672
13 27Mar - 2Apr 1080
14 3Apr - 9Apr 383
15 10Apr - 16Apr 0
16 17 - 23Apr 0
17 24Apr -30Apr 892
18 1May - 8May 1526
19 9May - 15May 894

Milestones

Highlights

  1. Install new hardware (Larger, 1.5m x 40cm & Faster - double)
    1. Since Dec 2022 our average scan rate is 100 panels/day
    2. New scanner ⬆️170 - 190 panels/day. ~70% improvement

Untitled

  1. Found new defective tiles submit pictures to Roman

Link to Defect file

Plan Next week

  1. Continue work on Side A

Issues

Open Action

Untitled