GOAL - Complete project by 31 Dec 2022
| WW | Date | Exterior | Interior |
|---|---|---|---|
| 9760 | 200 | ||
| Completed to date | 4222 | 203 | |
| % completion | 43.3% | 100% | |
| 40 | 3Oct - 9Oct | 103 | 127 |
| 41 | 10Oct - 16Oct | 90 | 127 |
| 42 | 17Oct - 23Oct | 70 | 127 |
| 43 | 24Oct - 30Oct | 112 | 127 |
| 44 | 31st - 6Nov | 372 | 127 |
| 45 | 7Nov - 13Nov | 287 | 127 |
| 46 | 14Nov - 20Nov | 579 | 127 |
| 47 | 21Nov - 27Nov | 534 | 140 |
| 48 | 28Nov - 5Dec | 675 | 145 |
| 49 | 6Dec - 10Dec | 509 | 201 |
| 50 | 11 Dec -19 Dec | 476 | 201 |
| 51 | 20 Dec - 26 Dec | 336 | 203 |